Garth-Lenz-5747-1.jpg

BREAKING: Site C Dam $600 Million Over Budget, Will Miss River Diversion Timeline, Says BC Hydro CEO

BC Hydro’s new CEO Chris O’Riley has written a letter to the B.C. Utilities Commission stating that the crown corporation will not meet the timeline for river diversion for the Site C dam, which will add $610 million to the project’s price tag.

“BC Hydro has encountered some geotechnical and construction challenges on the project and the risk to the river diversion timeline has now materialized,” O’Riley wrote.

“Based on the recent completion of a constructability review and an executive meeting with our Main Civil Works contractor on September 27, 2017, we have now determined that we will not be able to meet the current timeline for river diversion in 2019.”

The letter was in response to questions set out in the BCUC’s preliminary report issued on Sept. 20th.

ICYMI: What That 205-Page BCUC Report on the Site C Dam Actually Said

“Not meeting the current river diversion timeline has created new pressures on the project’s budget. We estimate that this development in the project is expected to increase its cost by 7.3 per cent or $610 million, for a total forecast project cost of $8.945 billion,” reads the letter.

BC Hydro had identified risks to the river diversion timeline in its August 30 filing with the B.C. Utilities Commission. An independent audit by Deloitte also identified the risk.

"BC Hydro are finally being a bit more transparent. It’s what we had expected for some time that this project has been mismanaged," said former BC Hydro CEO Marc Eliesen.

The Site C dam is the most expensive public project in B.C. history and, if completed, will flood more than 100 kilometres of river valley, destroying farmland and First Nations spiritual sites.

“Today’s filing provides an opportunity for us to share new information with the commission and the public,” O’Riley wrote in his letter. “Like all large, complex projects, Site C faces risks and uncertainties.”

The letter also notes that while the delay will set some activities back a year, there was a one-year float built into the schedule and BC Hydro is “confident we can still deliver this project ton time by November 2024.”

But Eliesen says that’s not a credible claim.

“There’s no way they’re going to meet the 2024 deadline. Keep in mind we’ve only completed two years of a nine-year project. We’ve got seven years to go with all of the problems and challenges and geo-technical issues,” Eliesen told DeSmog Canada.

The BC Hydro letter also notes that “due to the project’s complexity, we expect to continue to face risks in other areas, including our second largest procurement (i.e. the Generating Station and Spillway) that remains open and the highway realignment.”

Eliesen estimates the final price tag on Site C will escalate to $12 billion if the project is not terminated.

ICYMI: Revealed: Inside the B.C. Government's Site C Spin Machine

ICYMI: EXCLUSIVE: B.C. Government Broke Law to Expedite Site C Dam Construction, Legal Experts Say

“It is following almost the identical track that the other two major hydro projects in Canada — Keeyask in Manitoba and Muskrat Falls — have followed.”

Those two projects have been struck by major cost overruns and delays.

Despite the challenges Site C is facing, the letter states that BC Hydro’s analysis “continues to confirm that completing Site C as planned is still the most cost-effective option for our customers.”

“We remain committed to Site C and are confident in our ability to deliver the project,” the letter reads.

Eliesen finds that conclusion “totally bizarre” and credits the “very good work” of the Deloitte consultants for forcing BC Hydro to admit the project is over budget and behind schedule.

“To try to complete this project at this time is throwing good money at bad,” he said. “All of the evidence that’s coming out from this inquiry is that we don’t need the power.”

DeSmog Canada first reported on June 30, 2016, that the Site C dam was behind schedule and over budget. Documents obtained via Freedom of Information legislation later revealed a co-ordinated attempt by BC Hydro and the Premier's Office to discredit the story.

Image: Site C dam construction June 2016. Photo: Garth Lenz|DeSmog Canada

Another year of keeping a close watch
Here at The Narwhal, we don’t use profit, awards or pageviews to measure success. The thing that matters most is real-world impact — evidence that our reporting influenced citizens to hold power to account and pushed policymakers to do better.

And in 2024, our stories were raised in parliaments across the country and cited by citizens in their petitions and letters to politicians.

In Alberta, our reporting revealed Premier Danielle Smith made false statements about the controversial renewables pause. In Manitoba, we proved that officials failed to formally inspect a leaky pipeline for years. And our investigations on a leaked recording of TC Energy executives were called “the most important Canadian political story of the year.”

As the year draws to a close, we’d like to thank you for paying attention. And if you’re able to donate anything at all to help us keep doing this work in 2025 — which will bring a whole lot we can’t predict — thank you so very much.

Will you help us hold the powerful accountable in the year to come by giving what you can today?
Another year of keeping a close watch
Here at The Narwhal, we don’t use profit, awards or pageviews to measure success. The thing that matters most is real-world impact — evidence that our reporting influenced citizens to hold power to account and pushed policymakers to do better.

And in 2024, our stories were raised in parliaments across the country and cited by citizens in their petitions and letters to politicians.

In Alberta, our reporting revealed Premier Danielle Smith made false statements about the controversial renewables pause. In Manitoba, we proved that officials failed to formally inspect a leaky pipeline for years. And our investigations on a leaked recording of TC Energy executives were called “the most important Canadian political story of the year.”

As the year draws to a close, we’d like to thank you for paying attention. And if you’re able to donate anything at all to help us keep doing this work in 2025 — which will bring a whole lot we can’t predict — thank you so very much.

Will you help us hold the powerful accountable in the year to come by giving what you can today?

Glyphosate use in B.C. forestry, explained

Get the inside scoop on The Narwhal’s environment and climate reporting by signing up for our free newsletter. For decades, forestry companies in B.C. have used...

Continue reading

Recent Posts

Our newsletter subscribers are the first to find out when we break a big story. Sign up for free →
An illustration, in yellow, of a computer, with an open envelope inside it with letter reading 'Breaking news.'
Cartoon title: Risks of reading The Narwhal. Illustration of a woman sitting with a computer that has a Narwhal sticker on a park bench. A narwhal sitting next to her reads her computer screen over the shoulder. Text reads: "Wait — the government did WHAT?"
More than 800 readers have already stepped up in December to support our investigative journalism. Will you help us break big stories in 2025 by making a donation this holiday season?
Every new member between now and midnight Friday will have their contributions doubled by two generous donors.
Let’s match
Every new member between now and midnight Friday will have their contributions doubled by two generous donors.
Let’s match
Cartoon title: Risks of reading The Narwhal. Illustration of a woman sitting with a computer that has a Narwhal sticker on a park bench. A narwhal sitting next to her reads her computer screen over the shoulder. Text reads: "Wait — the government did WHAT?"
More than 800 readers have already stepped up in December to support our investigative journalism. Will you help us break big stories in 2025 by making a donation this holiday season?