Horgan to Hydro: Don’t Sign New Site C Contracts or Evict Residents

B.C. NDP Leader John Horgan has written to B.C. Hydro CEO Jessica McDonald to urge the crown corporation not to finalize any contracts or evict any residents to make way for the Site C dam until a new government is in place.

“I note that the majority of British Columbians who voted in this election voted for parties that want to see the Site C project reviewed or stopped,” Horgan wrote to McDonald.

A co-operation agreement between the B.C. NDP and Green Party released this week indicated that if the NDP forms government, Site C will immediately be sent for an expedited review by the B.C. Utilities Commission.

However, construction will not be paused during the review, which has led to concerns that irreversible harm could be done to the Peace Valley in the coming months. Enter today’s letter to McDonald.

“I write to you today to express my concern regarding impacts on the community of Bear Flat, the West Moberly First Nation, the Prophet River First Nation, and other families and communities impacted by the government’s decision to expropriate lands for the advancement of Site C,” Horgan wrote.

B.C. Hydro recently extended the leases for some families in the Peace Valley by one month beyond the original May 31st eviction date.

“While this is a welcome respite, I believe there is no demonstrated short term need to force these families from their homes, and because the status of the next governments of British Columbia are uncertain, the threat of imminent removal of residents from their expropriated homes and property is unreasonable,” Horgan wrote.

“Given what the Premier has characterized as a probable change in government over the coming weeks, we urge BC Hydro to suspend the evictions from these lands and grant a further extension on the timeline so that impacted families can stay in their homes until the future of Site C is firmly determined.”

With a price tag of $9 billion, the Site C dam is the most expensive public infrastructure project in B.C.’s history. The reservoir created by the dam will flood 107 kilometres of the Peace River. Experts have raised questions about the cost of the project and need for the power.

B.C. Hydro has faced several federal orders for failing to comply with environmental conditions, the most recent order being issued this week and coming with the threat of a $400,000 fine.

Horgan also raised concerns about any moves that would increase the liability of B.C. Hydro and ratepayers.

“We urge B.C. Hydro not to finalize any contracts that do not contain a penalty-free cancellation clause until a new government has gained the confidence of the legislature to govern and decide future policy regarding the Site C project."

Another year of keeping a close watch
Here at The Narwhal, we don’t use profit, awards or pageviews to measure success. The thing that matters most is real-world impact — evidence that our reporting influenced citizens to hold power to account and pushed policymakers to do better.

And in 2024, our stories were raised in parliaments across the country and cited by citizens in their petitions and letters to politicians.

In Alberta, our reporting revealed Premier Danielle Smith made false statements about the controversial renewables pause. In Manitoba, we proved that officials failed to formally inspect a leaky pipeline for years. And our investigations on a leaked recording of TC Energy executives were called “the most important Canadian political story of the year.”

We’d like to thank you for paying attention. And if you’re able to donate anything at all to help us keep doing this work in 2025 — which will bring a whole lot we can’t predict — thank you so very much.

Will you help us hold the powerful accountable in the year to come by giving what you can today?
Another year of keeping a close watch
Here at The Narwhal, we don’t use profit, awards or pageviews to measure success. The thing that matters most is real-world impact — evidence that our reporting influenced citizens to hold power to account and pushed policymakers to do better.

And in 2024, our stories were raised in parliaments across the country and cited by citizens in their petitions and letters to politicians.

In Alberta, our reporting revealed Premier Danielle Smith made false statements about the controversial renewables pause. In Manitoba, we proved that officials failed to formally inspect a leaky pipeline for years. And our investigations on a leaked recording of TC Energy executives were called “the most important Canadian political story of the year.”

We’d like to thank you for paying attention. And if you’re able to donate anything at all to help us keep doing this work in 2025 — which will bring a whole lot we can’t predict — thank you so very much.

Will you help us hold the powerful accountable in the year to come by giving what you can today?

‘Heartbreaking’ loss of newborn orca spurs renewed call for federal emergency order

Get the inside scoop on The Narwhal’s environment and climate reporting by signing up for our free newsletter. Wildlife biologist Brad Hanson was worried about the...

Continue reading

Recent Posts

Our newsletter subscribers are the first to find out when we break a big story. Sign up for free →
An illustration, in yellow, of a computer, with an open envelope inside it with letter reading 'Breaking news.'
Your access to our journalism is free — always. Sign up for our weekly newsletter for investigative reporting on the natural world in Canada you won’t find anywhere else.
'This is not a paywall' text illustration, in the black-and-white style of an album warning label
Your access to our journalism is free — always. Sign up for our weekly newsletter for investigative reporting on the natural world in Canada you won’t find anywhere else.
'This is not a paywall' text illustration, in the black-and-white style of an album warning label