Progress-Energy-Lily-Dam-1.jpg

Fracking Company Ordered to Drain Two Unauthorized Dams in B.C.’s Northeast

This article was originally published by the Canadian Centre for Policy Alternatives.

The provincial government has ordered Progress Energy to drain virtually all of the water trapped behind two massive dams the company built in violation of key provincial regulations.

The company was told on October 31 to drain all but 10 per cent of the water stored behind its Town and Lily dams near the Alaska Highway north of Fort St. John by Chris Parks, assistant director of compliance and enforcement with B.C.’s Environmental Assessment Office (EAO).

The order comes after Progress Energy filed an extraordinary application this summer with the EAO asking the provincial environmental regulator to retroactively “exempt” the two dams from required environmental assessments. Both dams are higher than five-storey buildings.

By law, Progress should have filed its exemption applications well before the projects were built, not after. Progress built its Town dam in 2012 and its Lily dam in 2014.

Both are part of a vast network of unlicensed dams that the Canadian Centre for Policy Alternatives (CCPA) first reported in early May have been built across northeast B.C. by fossil fuel companies to trap massive amounts of freshwater used in gas drilling and fracking operations.

ICYMI: A Dam Big Problem: Fracking Companies Build Dozens of Unauthorized Dams in B.C.'s Northeast

Numerous organizations, including the Blueberry River First Nation (BRFN), on whose traditional territory the dams were built, have written to the EAO objecting to Progress’ exemption request.

“BRFN has been repeatedly sounding alarm bells to the Crown (including through affidavits filed in court) about the diminished water quantity in our territory,” wrote Blueberry River First Nations lands manager Norma Pyle. “We have been watching lake levels drop, muskeg disappear, mineral licks dry up and streams reduce to small versions of their former selves.”

"Blueberry’s concern goes beyond these two dams to the failure of regulatory oversight in their territory — it’s not just these two dams, but dozens of them,” Blueberry River legal counsel Maegan Giltrow added in a separate e-mail statement.

“This is in the face of Blueberry’s repeated concerns to the Crown about the diminishing water quality and quantity they are seeing. This September the Blueberry River itself ran dry — Blueberry members haven’t seen that before. Meanwhile, hundreds of thousands of cubic meters of freshwater in their territory is being illegally impounded for oil and gas operations.”

“And Blueberry had to learn about the problem from media reports — where was the regulator? The Nation still doesn’t have answers to the questions it has put to the Oil and Gas Commission about all the illegal dams and water use."

Public Inquiry into Fracking Needed

The presence of the dams — and a host of additional issues relating to how Progress Energy and other fossil fuel companies use the water stored in them for their fracking operations — are among the concerns that triggered a call this week by 17 organizations (including the CCPA) for a full public inquiry into natural gas industry fracking operations in B.C.

In addition to the proliferation of unlicensed dams, the call for an inquiry was prompted by troubling events in the northeast of the province, including evidence of powerful earthquakes triggered by fracking, escalating water usage at B.C. fracking operations, rapidly increasing methane releases at gas well sites, local health impacts and ongoing impacts to First Nation lands.

ICYMI: Coalition Calls for Public Inquiry Into B.C. Fracking

The groups encouraged the government to examine the impacts of fracking and related operations on First Nation lands and resources in particular.

“We are deeply troubled that this dam-building free-for-all occurred on First Nation lands, that First Nations were not fully consulted about the true size and extent of these dams, and that our Indigenous Title, Rights and Treaty rights are still completely ignored or denied. There are still no substantive or meaningful opportunities to fully participate in decisions around how water resources are managed in our respective territories,” said Grand Chief Stewart Phillip, President of the Union of B.C. Indian Chiefs.

“We need a credible, strong, independent inquiry to get to the bottom of this.”

The Environmental Assessment Office has yet to say how it will respond to the Blueberry River First Nation’s letter and those of many other organizations urging the government to reject Progress’ application for exemptions. David Karn, a senior public affairs officer with the Ministry of Environment and Climate Change Strategy, said in an e-mail that he expects the EAO to make a decision about Progress’ exemption request “in early 2018.”

Both dams are considered “major projects” under B.C.’s Environmental Assessment Act because both exceed a critical height threshold of 15 metres. The Lily dam dramatically exceeds that threshold. It is 23 metres high or as tall as a seven-storey apartment building.

B.C.'s Environmental Assessment Office has ordered Progress Energy to drain almost all of the water from this unauthorized dam. Photo: Ben Parfitt

Build it First, Ask for Permission Later

Both dams are among more than 50 large earthen structures built by energy companies on Crown or public lands in northeast B.C. that are also subject to Treaty 8, the 1899 agreement reached between the Crown and the region’s First Nations.

Most or all of the dams were built without the companies first obtaining key provincial authorizations such as water licences. In addition, engineering specifications appear to never have been submitted to and approved by provincial authorities before the dams were constructed.

Dam safety and water licensing officials with the provincial Ministry of Forests, Lands and Natural Resource Operations are also investigating additional fracking dams that have been built on private lands, including farmlands within the provincial Agricultural Land Reserve. B.C.’s ALR was created in 1973 to preserve farmland.

It now falls to B.C.’s Oil and Gas Commission (OGC), which allowed the dams to be built without the proper permits first being obtained, to retroactively review dozens of pending water licence applications, and to assess the health, safety and environmental risks posed by dams that may not have been built to proper engineering standards.

The first batch of retroactive water licence applications came in late December last year when Progress Energy applied for 13 such licences on a single day.

Each application was for water rights at dams that had already been built and that were already impounding water. The applications did not include the water licence requests at the two dams currently under review by the EAO.

Recently, investigative journalist and author Andrew Nikiforuk reported how the OGC sent staff on a flyover of 51 unlicensed dams following publication of the CCPA’s initial research in May.

The inspections revealed serious problems at seven dams, or 14 per cent of those visited.

ICYMI: B.C. Regulator Finds Numerous Frack Water Dams Unsafe, At Risk of Failure

Progress Energy built five of the seven problematic dams (these five do not include the two before the EAO) and ConocoPhillips built the other two.

Noted problems included erosion, slumping and water overflowing the top of some dams.

According to documents obtained through numerous Freedom of Information requests filed by the CCPA, all of the unauthorized dams were purpose-built to trap freshwater used in fracking operations, where huge quantities of water are pumped under intense pressure to fracture or crack open deep rock formations so that trapped methane gas is released.

During a Progress Energy fracking operation north of Fort St. John in 2015, 160,000 cubic metres of water — the equivalent of 64 Olympic swimming pools — was pressure pumped underground at a fracking operation, triggering a 4.6 magnitude earthquake.

Dam Safety at Issue

The EAO’s order to Progress requiring it to drain its Town and Lily dams does not speak directly to the issue of how safe or unsafe those structures may be. Nor does it speak to the broader question of how the dams came to be built under the OGC’s watch, or whether or not the dams may be at risk because of ground motions triggered by nearby fracking operations.

The order notes, however, that “an environmental assessment certificate has not been issued for the dams” and because a certificate has not been issued, the Environment Minister “may order that the construction, operation, modification, dismantling, or abandonment of the project cease, either altogether or to the extent specified by the Minister, until the proponent obtains an environmental assessment certificate.”

Progress is then ordered to:

  1. Maintain water volumes stored by the dams at no more than 10 per cent of live storage capacity unless otherwise directed by the EAO’s compliance and enforcement division/branch.
     
  2. Monitor and record water volumes on a weekly basis during frozen conditions and on a daily basis during conditions where flowing surface water is present, and provide that information to EAO compliance and enforcement upon request.

Following this order, Progress Energy’s president and CEO Mark Fitzgerald issued a statement to the Globe and Mail claiming “that it was his own company that identified problems with some of its dams — including the failure to obtain proper authorizations — and brought the findings to the attention of the provincial government.”

The article continued: “He said an engineering review of the company’s water-holding facilities found no structural issues, but noted that some were larger than permits allowed.”

"We own those mistakes, and are working with the [Oil and Gas Commission] to correct them," Fitzgerald said to the Globe and Mail.

“What's important to me is that we will not make these mistakes again. We're committed to working closely with the regulators and to managing our operations in an environmentally responsible manner."

An unauthorized Progress Energy dam where millions of gallons of freshwater was found impounded in early April. It is among “dozens” of unpermitted dams spread across northern B.C. Photo © Garth Lenz, all rights reserved.

Self-reporting Doubts

But records obtained from the Oil and Gas Commission through the CCPA’s various Freedom of Information requests paint a different picture.

Progress Energy did not suddenly arrive at the conclusion that some of its dams were built without the required authorizations.

Rather, the company — along with all its competitors operating in northeast B.C. — was told by the OGC in May 2016 to submit lists of all dams that it had built. Why the OGC apparently didn’t know the answer to the question is not clear.

Two months later, after the companies had reported back to the Commission, then OGC chief hydrologist, Allan Chapman, wrote an e-mail to the Commission’s vice-president of applications, James O’Hanley, and its vice-president of operations, Lance Ollenberger, stating:

“Hi James and Lance. Progress Energy has confirmed that they built two Freshwater Storage Sites that exceed the EA Reviewable Projects Regulation of 15 metres. In their submission from Wednesday, they indicate that one is 23 metres, which is quite breathtaking. I have advised them they need to contact the EAO.”

So clearly, the company did not voluntarily approach the Environmental Assessment Office. It was compelled to do so by the regulator, which should have prevented the dam from being built in the first place.

Several problems with the Lily dam were also subsequently noted by Progress Energy in its own commissioned engineering report submitted to the EAO. The Lily Dam Project Description document noted signs of seepage, or water leaking from behind the dam’s walls, and improperly graded water outlets for the dam. According to the engineering report, both issues had the potential to cause severe damage to — or failure of — the dam, if left unaddressed.

Whether those troubling words of warning influenced the Environmental Assessment Office’s decision to order Progress to drain most of the water from its two largest dams is unknown.

If the company's application for exemption is ultimately denied and the two dams are finally subjected to a full provincial environmental assessment, the answer to that question and more may finally see the light of day.

Even so, this case drives home why B.C. needs a full public inquiry into fracking activities.

Image: The Lily Dam wa built by Progress Energy without a provincial environmental permit. Photo: Progress Energy

We’ve got big plans for 2024
Seeking out climate solutions, big and small. Investigating the influence of oil and gas lobbyists. Holding leaders accountable for protecting the natural world.

The Narwhal’s reporting team is busy unearthing important environmental stories you won’t read about anywhere else in Canada. And we’ll publish it all without corporate backers, ads or a paywall.

How? Because of the support of a tiny fraction of readers like you who make our independent, investigative journalism free for all to read.

Will you join more than 6,000 members helping us pull off critical reporting this year?
We’ve got big plans for 2024
Seeking out climate solutions, big and small. Investigating the influence of oil and gas lobbyists. Holding leaders accountable for protecting the natural world.

The Narwhal’s reporting team is busy unearthing important environmental stories you won’t read about anywhere else in Canada. And we’ll publish it all without corporate backers, ads or a paywall.

How? Because of the support of a tiny fraction of readers like you who make our independent, investigative journalism free for all to read.

Will you join more than 6,000 members helping us pull off critical reporting this year?

Ontario could run out of landfill space in nine years. Then what?

Ontario’s garbage is making headlines again as a small farming town tries to ward off a large construction company’s efforts to revive and expand a...

Continue reading

Recent Posts

Thousands of members make The Narwhal’s independent journalism possible. Will you help power our work in 2024?
Will you help power our journalism in 2024?
… which means our newsletter has become the most important way we connect with Narwhal readers like you. Will you join the nearly 90,000 subscribers getting a weekly dose of in-depth climate reporting?
A line chart in green font colour with the title "Our Facebook traffic has cratered." Chart shows about 750,000 users via Facebook in 2019, 1.2M users in 2020, 500,000 users in 2021, 250,000 users in 2022, 100,000 users in 2023.
… which means our newsletter has become the most important way we connect with Narwhal readers like you. Will you join the nearly 90,000 subscribers getting a weekly dose of in-depth climate reporting?
A line chart in green font colour with the title "Our Facebook traffic has cratered." Chart shows about 750,000 users via Facebook in 2019, 1.2M users in 2020, 500,000 users in 2021, 250,000 users in 2022, 100,000 users in 2023.
Overlay Image