It would have been the first 100 per cent community-owned renewable power project in North America.

Located just south of Swift Current, Sask., the $90-million project would have generated 35 megawatts (MW) of electricity from wind turbines and solar panels with electricity sold to the provincial utility, SaskPower.

But SaskPower had other plans for the region — specifically, a $700-million natural gas power station.

On Dec. 2, it was announced that the gas power station — which will emit one million tonnes of greenhouse gases annually, equivalent to putting 211,000 cars on the road for a year — wouldn’t require a federal environmental assessment.

Two days later, SaskWind, the provincial wind energy association and key promoter of the proposed Swift Current wind and solar project, shut down after four years of operation.

In a final blog post, SaskWind president James Glennie wrote that the decision about the environmental assessment of the natural gas power station was Tweet: Sask. power station decision ‘extremely disappointing, includes no justification & verges on inexplicable’ http://bit.ly/2hUuzY8 #skpoli“extremely disappointing, includes no justification and verges on the inexplicable.”

The gas-fired power plant is proposed to open in 2019 just northwest of Swift Current and generate 350 MW, ten times more electricity than the renewable project.

The Canadian Environmental Assessment Agency’s decision not to review the gas power station was the final straw for SaskWind, Glennie told DeSmog Canada in an interview.

Many other factors added up to “stonewall” his organization’s push for community-owned wind power, despite the fact that Saskatchewan has an excellent wind resource.

SaskPower and the provincial government “refused to acknowledge our existence in four years,” Glennie said.

“We couldn’t have a debate or discussion with them.”

The story of SaskWind’s failed push for community-led renewable energy is about much more than one lost wind project — it’s about how better, cheaper, more sustainable and more democratic energy choices are pushed aside to maintain the status quo.

It’s a problem that’s plagued many of Canada’s provinces, like B.C. where a primary focus on hydroelectric development has forced out wind and solar power producers, or Ontario where large-scale nuclear and hydro kept small-scale and community-led energy production at bay for years.

Saskatchewan’s community-led wind projects could help the province break the spell, but first they’d have to be given the chance.

SaskPower’s Fossil Fuel Tunnel Vision

Glennie’s dream of a community-owned wind project in Saskatchewan seemed like a win-win-win. Job creation, emissions reductions and provincial profit retention are among the many benefits SaskWind outlines on its website.

But the province put up two big barriers, according to Glennie.  

First, SaskPower has historically prioritized fossil fuel projects. Second, the province prioritizes utility-scale energy production (around 50 MW or larger) to the exclusion of smaller, community-led initiatives.

In 2015, 42 per cent of Saskatchewan’s power came from coal-fired power plants and 34 per cent from natural gas. Only 2.9 per cent was generated by wind.

Rather than switching to less polluting forms of energy, the province has focused heavily on the controversial technique of carbon capture and storage (CCS) and building new natural gas power plants.

Boundary Dam CCS Doubled Cost of Power, Plagued With Design Flaws

Carbon capture and storage is a process which captures carbon emissions primarily from coal-fired power plants for sequestration underground or to be used in oil and gas recovery. But the technology, which is costly, hasn’t been able to achieve the full-scale commercial success industry hoped.

In recent years 43 CCS projects worldwide have been cancelled, put on hold or simply gone dormant.

SaskPower’s carbon capture and storage project at the Boundary Dam coal power plant, which the province promised would provide “clean” coal-powered electricity, cost nearly $1.5 billion to build, effectively doubling the cost of power from $0.06 per kilowatt hour (kWh) to $0.12 per kWh from the facility.

SaskPower has since received multiple approvals for rate increases from the provincial government.

“It’s certainly not competitive with wind,” says Mark Bigland-Pritchard, co-author of the report SaskPower's Carbon Capture Project What Risk? What Reward?

“Just coal by itself is only barely competitive with wind given the wind speeds and capacity factors that we can achieve in Saskatchewan.”

According to the U.S. Energy Information Administration (EIA), the levelised cost of new generation capacity for coal with CCS is $139.50 per megawatt hour. Natural gas costs $55.80 per megawatt hour, but doesn’t include any price on carbon.

Meanwhile, wind power costs $58.50 per megawatt hour, or about 42 per cent of the price of coal with CCS.

Brett Dolter, vice-president at the Canadian Society for Ecological Economics, says carbon capture on coal is “one of the priciest ways to meet emissions reductions” and that it would be far more prudent to increase wind capacity and use gas and hydro as backup.

“If we look at a more Canadian perspective, it might make sense for Saskatchewan to even overbuild wind and export it to Alberta to help them get off of coal,” he says. “It’s such a great wind resource and right next-door.”

SaskPower Only Seeking Utility-Scale Renewables in RFP Process

This is where the second source of “stonewalling” community-owned wind power comes in.

Saskatchewan has set a target of 50 per cent generation capacity from renewables by 2030, requiring an increase of wind power from five per cent of capacity to 30 per cent.

Robert Hornung — president of the Canadian Wind Energy Association (CanWEA) — says Saskatchewan plans to procure about 1,600 MW of wind between now and 2030, which represents a “very significant and important short-term growth opportunity for the industry.”

(That’s in contrast to British Columbia, which CanWEA pulled out of in February because the provincial government’s decision to proceed with the Site C dam and other hydroelectric projects has effectively “crowded out the need for other forms of generation” until 2030.)

SaskPower is explicitly looking for utility-scale wind projects, mostly between 100 and 200 MW.

In a statement provided to DeSmog Canada, a SaskPower spokesperson said: “We do not have any specific plans for community wind projects and we are asking community projects to submit to the request for qualification, the same as all other proponents.”

But a minimum requirement of the request for qualification (RFQ) process — which will start in the first quarter of 2017 — is “experience in utility scale wind projects.”

That clearly discounts organizations like SaskWind.

“By definition there are none in the province that [qualify],” Glennie says.

A report by Adrienne Baker of Canadian Clean Energy Conferences noted this process could result in "many developers competing for a relatively small number of contracts,” with the implication being that resulting contracts would be for large megawatt wind farms, rather than community-scale projects.

Procuring wind with big request for proposal (RFP) tender processes has indeed worked; Hornung notes there’s been 10,000 MW of wind installed across the country in the last decade.

That’s come mostly from utility-scale wind farms owned by the likes of EDF Énergies Nouvelles, Capital Power, TransAlta and Brookfield Renewable Power. Nova Scotia did see significant success with its feed-in tariff for community-owned renewables (which was recently cancelled by the provincial Liberals).

“The procurement processes that we have in Canada that tend to focus very much on securing the lowest-cost power does tend to favour in a relative sense the utility-scale projects because they can capture some economies of scale that community-scale projects can’t,” Hornung said.

A 177 MW utility-scale wind project recently on the table in southwestern Saskatchewan was projected to cost $355 million, or one MW for every $2 million in capital costs. That’s a cheaper relative investment compared to the proposed 30 MW Swift Current project, at $90 million, or one MW for every $3 million in upfront investment.

Community-Owned Wind Generates More Local Support and Jobs

Yet there can be significant downsides to a top-down approach that can push community-level concerns to the wayside.

For one, it doesn’t generate as many local jobs; a 2014 report by the Institute for Local Self-Reliance indicated that community-owned wind projects create an average of twice as many jobs as "absentee-owned wind projects."

Because of this, there is some tension between large-scale wind energy producers represented by CanWEA, which include major players like TransAlta, Brookfield and Enbridge, and community wind energy advocates like SaskWind.

For Glennie, not having that community component can be detrimental to wind energy projects, something Ontario has experienced over the last decade.

There are now dozens of anti-wind organizations in Ontario, which boasts 3,923 MW in generation capacity from wind.

In late September, Ontario scrapped $3.8 billion of planned renewable procurements amid severe anti-wind backlash. Only two weeks later, a NAFTA tribunal awarded $28 million to Windstream Energy LLC after Ontario deferred plans for offshore wind development in 2011.

“Ontario doesn’t exactly have a stunning reputation of doing wind and solar,” he says. “It’s like ‘right, where we can screw up next? Let’s try Saskatchewan.’ ”

As Chris Turner noted in a 2015 article for The Walrus, Ontario’s Green Energy Act has been made "effectively defunct" and the key feed-in tariff gone.

Turner argued that much of the failure of the province’s Green Energy Act has to do with the institutional culture of massive Crown corporations, which tended to focus on large-scale nuclear and hydro projects at the expense of decentralized renewables.

Apparently the same type of “fiefdom,” as Turner calls it, is present in Saskatchewan.

“SaskPower is still built on that old sort of command-and-control approach that so many utilities have,” Bigland-Pritchard says.

There is already indication that some of the mistakes made with wind energy in Ontario could be repeated in Saskatchewan. In mid-September, an Ontario-based wind company planning to build the aforementioned 177 MW wind farm in southwestern Saskatchewan was rebuffed by local environmentalists concerned about impacts on migratory birds.

SaskPower plans to relocate the project.

Community Ownership as a Social Acceptance Strategy

It may be a sign of things to come.

“I don’t understand what the thinking was in SaskPower’s mind when they rejected [community-owned projects],” says Cathy Sproule, NDP opposition critic for the environment and SaskPower.

“It’s unfortunate. I like the idea of allowing communities to engage in this process, and I think you get better buy-in when wind projects go up.”

A SaskPower spokesperson notes that 20 MW of solar will be added to the grid by 2021 via community-based projects, with another 20 MW from First Nations communities.

That’s a practical objective: southeast Saskatchewan, where many of the coal-fired power plants are located, is one of the sunniest places in Canada, making it an excellent spot for solar.

But electricity demand in Saskatchewan peaks in the winter, and solar output is lowest then because of fewer hours of sunlight. Conversely, wind speeds are highest in the winter.

As Dolter notes: “Wind aligns better with the demand profile than solar.”

“Community ownership might be almost more of a social acceptance strategy than an economic strategy,” Dolter says.

“If you’ve got a rural municipality in Saskatchewan who has an ownership stake in wind, that municipality might be a lot happier with it than they are in Ontario where the ability for municipalities to say ‘no’ to wind projects was removed.”

Image: A wind energy worker services a turbine in Colorado. Photo: Dennis Schroder/National Renewable Energy Laboratory

Like a kid in a candy store
When those boxes of heavily redacted documents start to pile in, reporters at The Narwhal waste no time in looking for kernels of news that matter the most. Just ask our Prairies reporter Drew Anderson, who gleefully scanned through freedom of information files like a kid in a candy store, leading to pretty damning revelations in Alberta. Long story short: the government wasn’t being forthright when it claimed its pause on new renewable energy projects wasn’t political. Just like that, our small team was again leading the charge on a pretty big story

In an oil-rich province like Alberta, that kind of reporting is crucial. But look at our investigative work on TC Energy’s Coastal GasLink pipeline to the west, or our Greenbelt reporting out in Ontario. They all highlight one thing: those with power over our shared natural world don’t want you to know how — or why — they call the shots. And we try to disrupt that.

Our journalism is powered by people just like you. We never take corporate ad dollars, or put this public-interest information behind a paywall. Will you join the pod of Narwhals that make a difference by helping us uncover some of the most important stories of our time?
Like a kid in a candy store
When those boxes of heavily redacted documents start to pile in, reporters at The Narwhal waste no time in looking for kernels of news that matter the most. Just ask our Prairies reporter Drew Anderson, who gleefully scanned through freedom of information files like a kid in a candy store, leading to pretty damning revelations in Alberta. Long story short: the government wasn’t being forthright when it claimed its pause on new renewable energy projects wasn’t political. Just like that, our small team was again leading the charge on a pretty big story

In an oil-rich province like Alberta, that kind of reporting is crucial. But look at our investigative work on TC Energy’s Coastal GasLink pipeline to the west, or our Greenbelt reporting out in Ontario. They all highlight one thing: those with power over our shared natural world don’t want you to know how — or why — they call the shots. And we try to disrupt that.

Our journalism is powered by people just like you. We never take corporate ad dollars, or put this public-interest information behind a paywall. Will you join the pod of Narwhals that make a difference by helping us uncover some of the most important stories of our time?

Tea Creek is growing food security for B.C. First Nations — but its own future is ‘fragile’

Get the inside scoop on The Narwhal’s environment and climate reporting by signing up for our free newsletter. Jacob Beaton’s name has become closely tied...

Continue reading

Recent Posts

Our newsletter subscribers are the first to find out when we break a big story. Sign up for free →
An illustration, in yellow, of a computer, with an open envelope inside it with letter reading 'Breaking news.'
Your access to our journalism is free — always. Sign up for our weekly newsletter for investigative reporting on the natural world in Canada you won’t find anywhere else.
'This is not a paywall' text illustration, in a reddish-pink font colour
Your access to our journalism is free — always. Sign up for our weekly newsletter for investigative reporting on the natural world in Canada you won’t find anywhere else.
'This is not a paywall' text illustration, in a reddish-pink font colour